
OVERVIEW
Maintaining supply in Moturoa
With Transpower decommissioning its New Plymouth Power Station grid exit point, we needed to ensure ongoing electricity supply for our customers in the Moturoa area.
The best option for our customers was to install new 33kV cables from Transpower’s Carrington St grid exit point to our Moturoa zone substation. We worked with Transpower on this. We also replaced the switchgear and power transformers at Moturoa to ensure they kept working well (separate to the $10m cable investment).
During CPP – Year One we:
- Laid 6.5km of dual circuit ducting in open trenches along the cable route and reinstated the road
- Installed the 33kV cables in the ducts
- Constructed a new building, installed new larger transformers and begun installation of switchboards at Moturoa zone substation
The work was completed in December 2019.
The challenge
With Transpower decommissioning its New Plymouth Power Station grid exit point (GXP), we needed to ensure ongoing electricity supply for our customers in the Moturoa area.
The solution
The best option for our customers was to install new 33kV cables from Transpower’s Carrington St grid exit point, to our Moturoa zone substation – we worked with Transpower on this.
Separately, we also replaced the switchgear and power transformers at Moturoa to ensure effective operation.
Project Milestones:
- Laid 6.5km of dual circuit ducting in open trenches along the cable route
- Installed the 33kV cables in the ducts
- Constructed a new building, installed new larger transformers and begun installation of switchboards at Moturoa zone substation
The work was completed in December 2019.
The benefit
It’s an example of our investment in your future – providing our customers with a safe and reliable electricity supply to the Moturoa area.
Milestones
Construct new substation building
Route for new circuit between Arapuni and Putaruru confirmed
Planned power cut during this period
Construction of the circuit and new transformer at Putaruru substation
UPDATES
Find out the latest updates about this project
Working with you – Route options
Connecting with customers
Construct new substation building
FAQ
We strive to minimise impact in the design and placement of network infrastructure and we’re still planning and consulting on the route for the new circuit. The circuit will be a mix of overhead lines – which you will see, and underground cable – which you won’t see. You’ll also see a new building at our Putaruru substation, replacing the ageing existing building there.
EVENTS
Event 1
Event 2
Event 3
Downloads
2020
- Document 1
- Document 2
- Document 3