
OVERVIEW
To ensure safety and security of supply for our Hunterville customers we needed to replace poles, cross arms and overhead line along some of the more remote roads in the area.
The project presented a number of challenges – the work would require 15 planned outages for various customers. Because the roads were narrow we would also need to have traffic management and road closures in place so our crews could work safely, and manoeuvre equipment if required. On occasion, we would also need to helicopter in equipment.
The complex job required a unique solution. To reduce the impact to customers it was decided to work with three separate contractors; Obertech, Electrix and Downer to carry out the work as quickly and efficiently as we could.
Each contractor was responsible for a separate stretch of the works, allowing the maintenance to take place simultaneously along the road (see the map below) and minimise the time it would take to complete the maintenance.
Powerco thanks Hunterville customers for their co operation on this project.
Link to our glossary
The challenge
Conducting maintenance on overhead lines in a narrow and remote part of our network near Hunterville.
The solution
Engage three contractors to carry out the work simultaneously.
The benefit
Minimise impact to customers, by carrying out the maintenance as quickly and as efficiently as possible.
Milestones
Construct new substation building
Route for new circuit between Arapuni and Putaruru confirmed
Planned power cut during this period
Construction of the circuit and new transformer at Putaruru substation
UPDATES
Find out the latest updates about this project
Working with you – Route options
Connecting with customers
Construct new substation building
FAQ
We strive to minimise impact in the design and placement of network infrastructure and we’re still planning and consulting on the route for the new circuit. The circuit will be a mix of overhead lines – which you will see, and underground cable – which you won’t see. You’ll also see a new building at our Putaruru substation, replacing the ageing existing building there.
EVENTS
Event 1
Event 2
Event 3
Downloads
2020
- Document 1
- Document 2
- Document 3